Module I· Revenue Recognition (IFRS 15)Intermediate
Question
How does the percentage-of-completion method work?
Answer
PoC recognizes revenue by project progress, usually costs incurred divided by total estimated costs. It is valid only if IFRS 15 over-time criteria are met.
Deep diveShow more details
The key audit risk is management bias in estimated total cost. Small changes in cost-to-complete can materially move revenue, EBITDA, and backlog conversion.